Week 7: Bricks

Our bricks were delivered last week, but the brick crew our SS had booked in we’re still finishing another job so they didn’t get onsite until this week.

As expected, progress has slowed down now. About 2/3 of the ground floor walls are bricked along the wall closest to our neighbour, back of the house and near the kitchen. Progress hasn’t started on the front facade yet.

We can also see that all the internal plumbing has been completed, some of the pipes are visible along the outside walls.

Next week the ground floor bricks are due to finish then we will have a couple of weeks with no action after our scaffold goes up as the brick crew will go to work another house before returning to finish our 2nd storey. Adding that all up it seems unlikely we will see our bricks finished until close to the end of May.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s