Timeline

02/07/16Holding deposit on land

10/07/16 – Land contract signed

26/07/16 – 5% deposit on land paid

29/07/16 – Land contracts exchanged

30/09/16Tender request and deposit to Wisdom Homes for Aspiration 31

11/11/16 – Tender presentation at Wisdom sales office and tender acceptance fee paid

14/11/16 – Tender revision #1 submitted to Head Office and request for first draft working drawings.

15/12/16 – Tender #2 received

16/12/16 – Selections appointments delayed to Feb/Mar 2017 to await working drawings

21/02/17 – First draft working drawing received

03/03/17 – Tender #2 / Variation #1 requested for drawing revisions

08/03/17 – Tender #2 / Variation #1 signed off for drawing revisions

30/03/17 – Second draft working drawings received – minor revisions requested

31/03/17 – Third draft working drawings received

31/03/17 – Land loan application started

02/04/17Contract and drawings signed, remained of 5% deposit paid

13/04/17 – Kitchen and Tiles/Flooring selections

02/05/17 – Electrical/Landscaping/Colours selections

05/05/17 – Staircase and Alarm/Home Theatre selections

06/05/17 – Walk your Lot/Meet the Neighbours event @ Willowdale

Late May/Early June 17 – Selections variations received

21/06/17 – Land loan application approved

17/07/17 – LPI subdivision plans lodged by Stockland

18/08/17 – LPI subdivision plans approved

31/08/17Land Registration

28/09/17 – Construction loan (Heritage) application started

13/10/17 – Plans submitted to CDC certifier for approval

01/11/17 – Progress Payments issue with construction loan (Heritage)

13/11/17 – Plans approved by CDC certifier

13/11/17 – Construction loan (Heritage) application abandoned

19/11/17 – Construction loan (CBA) application started

23/11/17 – Draft End Panel received

24/11/17 – Draft End Panel revised

25/11/17 – Draft End Panel signed off

10/12/17 – Construction loan (CBA) formal approval

21/12/17 – Final Construction Plans received

CHRISTMAS SHUTDOWN – 22/12/17 to 09/01/18

10/01/18 – Final Construction Plans signed off

17/01/18 – Land refinanced from Heritage to CBA

25/01/18 – Final End Panel received

28/01/18Final End Panel signed off

31/01/18 – Letter of Authority to Commence Construction received from CBA

01/02/18 – Production Estimating started

02/02/18 – Fence and Portaloo delivered

09/02/18 – Land levelled

23/02/18 – Piering completed and slab forms/waffle pods laid

27/02/18 – Slab laid

01/03/18 – OFFICIAL COMMENCEMENT OF CONSTRUCTION

16/03/18 – External plumbing and lead ins completed

21/03/18 – Frames delivered

23/03/18 – Ground floor frames completed

29/03/18 – Frames completed


UPCOMING MILESTONES

Bricks

Roof